We get the road occupancy licences and council approvals your project needs, and deal with each agency so your works or event are cleared to go ahead. We handle the Maroubra approvals from the ROL through to council sign-off, so works or events go ahead on schedule. See the full Council Permits & Approvals service, or browse all traffic management in Maroubra.
Traffic management in Maroubra
Anzac Parade carries high volumes between the city and the southern beaches, intersecting Maroubra Road at a node that also serves Pacific Square's retail catchment and the beach reserve car parks. Surf carnival weekends, summer beach-goer surges and routine utility works along this arterial corridor generate recurring needs for traffic-control plans and pedestrian-safety measures.
FAQ
Council Permits & Approvals — common questions
What is a Road Occupancy Licence (ROL) and when do I need one?
A Road Occupancy Licence is formal Transport for NSW approval to occupy or affect the state (classified) road network. You generally need one to work on a state road, within 100 m of traffic signals, or wherever works affect traffic flow, queues or safety on a state road. Council-controlled local roads are approved by the council instead, and the ROL application must match your TGS.
What's the difference between work on a local road and a classified (state) road?
The road type decides who approves you. Works on a council-controlled local road are approved by that council, often through a Local Traffic Committee. Works on a classified (state) road, or within 100 m of traffic signals, require a Transport for NSW Road Occupancy Licence via the OPLINC system. Many jobs touch both, so the approval path has to be mapped before work starts.
How long does approval take?
Transport for NSW advises Road Occupancy Licence applications are processed within about 10 business days of submission. Council approval of a TGS typically runs around 10-14 business days and can extend to about 28 days or more if state-managed roads or TfNSW are involved. Complex or non-compliant submissions take longer, so a correct site-specific plan the first time is the fastest path. These are current authority guidelines, not guarantees.
Do I need a Traffic Management Plan for my project or event?
You generally need a TMP or CTMP whenever works or an event will affect how traffic, pedestrians or cyclists move on a public road — for example lane or road closures, footpath closures, or construction traffic entering a busy street. For construction a CTMP is frequently a condition of development consent; for events a TMP is required if you're closing or significantly affecting public roads. If unsure, a quick site review will confirm which document your job needs.