We get the road occupancy licences and council approvals your project needs, and deal with each agency so your works or event are cleared to go ahead. Permits in Lane Cove mean Road Occupancy Licences, Local Traffic Committee endorsement and Roads Act closures. We manage each agency so the job is cleared to proceed. See the full Council Permits & Approvals service, or browse all traffic management in Lane Cove.

Traffic management in Lane Cove

Burns Bay Road and Longueville Road converge on Lane Cove town centre's retail strip, which sits directly above the Lane Cove Tunnel portals — creating a situation where surface works must be carefully staged to avoid disrupting tunnel ventilation infrastructure and the heavy traffic volumes the tunnel draws to the area. Retail activation events along the pedestrian mall and ongoing apartment development along the corridor generate a steady stream of traffic-management and council-permit requirements.

FAQ

Council Permits & Approvals — common questions

What is a Road Occupancy Licence (ROL) and when do I need one?

A Road Occupancy Licence is formal Transport for NSW approval to occupy or affect the state (classified) road network. You generally need one to work on a state road, within 100 m of traffic signals, or wherever works affect traffic flow, queues or safety on a state road. Council-controlled local roads are approved by the council instead, and the ROL application must match your TGS.

What's the difference between work on a local road and a classified (state) road?

The road type decides who approves you. Works on a council-controlled local road are approved by that council, often through a Local Traffic Committee. Works on a classified (state) road, or within 100 m of traffic signals, require a Transport for NSW Road Occupancy Licence via the OPLINC system. Many jobs touch both, so the approval path has to be mapped before work starts.

How long does approval take?

Transport for NSW advises Road Occupancy Licence applications are processed within about 10 business days of submission. Council approval of a TGS typically runs around 10-14 business days and can extend to about 28 days or more if state-managed roads or TfNSW are involved. Complex or non-compliant submissions take longer, so a correct site-specific plan the first time is the fastest path. These are current authority guidelines, not guarantees.

Do I need a Traffic Management Plan for my project or event?

You generally need a TMP or CTMP whenever works or an event will affect how traffic, pedestrians or cyclists move on a public road — for example lane or road closures, footpath closures, or construction traffic entering a busy street. For construction a CTMP is frequently a condition of development consent; for events a TMP is required if you're closing or significantly affecting public roads. If unsure, a quick site review will confirm which document your job needs.

Get in touch

Need council permits & approvals in Lane Cove?

Tell us about the site, the dates and what you need — we'll come back with a plan.

Site plan, brief or photos — PDF, image, DOC, DWG or ZIP (max 5MB).